Re: Indirect labor

$
0
0

Hi Aryan

 

Already Rajneesh has give you a guideline just adding it in my view points:

 

 

No.of employee  5==>  Permanen Lab , 2 ==>Temp Lab,

These are direct contributors to the cost of the product and I want them to be displayed as separate line in the costestimate

 

....... Through Activity

         Create 2 act type PermLab & TempLab

         Plan in KP26/KP06

         Create Splitting structure for respective Prod deptts

         Process all planning execution upto cost estimation

 

        Tell your PP guy to incorporate 2 activity in Routing with proper assignment to identify permlab and temp lab seperately

 

Prod Mgmt , QC ,Admin & maintainece , these are all indirect cost

1) How do I bring them in the cost estimate

2) if point# 1 is wrong then how do I take care of this so that all those $ are contributed to the cost of the product

 

.......option 1. If you want to show this cost separately as indirect OH cost like Prod Mgmt cost, QC cost, Admn cost and Maint cost then create 4 CCtr as Prod Mgmt OH, QC oh etc and plan in KP06 and finally allocate these cost to prod deptt through assessment cycle. In CCS also create 4 separate attributes and assign relevant CE to identify in prod cost

 

 

.......option2. Create cost sheet and allocate in 4 category of OH cost.

I don't prefer any activity for indirect cost of this nature

 

 

 

Kamal