Hello,
If you are referring to Project versions , then you need to create project versions (CN72) and use the standard version reports in comparing operative parameters with baseline version.
Project scheduling is a standard PS functionality which ideally needs to happen regularly whenever any changes happens in active PS structure.
Shubham